Progress Report - Week 14 - ending Sunday 28th April 2024
Achievements during the week
-
Continue fit out and commissioning of electrics, fire alarms & emergency lighting
-
Commence Installation of suspended ceiling and light panels on first floor.
-
Lay carpet in new library area and build shelving units.
-
Start process of bringing items out of storage back to the club house