Progress Report - Week  2  -  ending Sunday 4th February 2024

Achievements during the week

  • Lighting and fire alarm system made safe, lighting units removed and above ceiling wiring stripped

  • Ceiling stripped out with panels and insulation prepared for storage and reuse

  • Club house floor cleared of all other items.

  • Workshop partition framework built

  • Emergency exit staircase partition framework built