Progress Report - Week 4 - ending Sunday 18th February 2024
Achievements during the week
-
Final levels for steel upright seating checked and adjusted as necessary
-
Steel Uprights of original structure drilled where required to enable floor support steel beams will be attached.
-
Steel beams delivered to site by supplier
-
Steel grid fully installed
-
First floor beams lifted into place and secured
-
First batch of floor sheeting lifted and moved into place ready to be secured