Progress Report - Week  4  -  ending Sunday 18th February 2024

Achievements during the week

  • Final levels for steel upright seating checked and adjusted as necessary

  • Steel Uprights of original structure drilled where required to enable floor support steel beams will be attached.

  • Steel beams delivered to site by supplier

  • Steel grid fully installed

  • First floor beams lifted into place and secured

  • First batch of floor sheeting lifted and moved into place ready to be secured