Progress Report - Week 6 - ending Sunday 3rd March 2024
Achievements during the week
-
The emergency exit staircase from the first floor at the rear of the building has been installed
-
Previous loft access hatch and ladder in the entrance hall removed
-
Ceiling of the toilets, kitchen and entrance hall removed
-
Drop the loft floor beams by approx 50mm cutting away brick work as necessary
-
Reinstate and re-fix beams over kitchen, toilets and entrance hall
-
Install level flooring over the entire loft area
-
Some of the loft contents loaded to skip for removal