Progress Report - Week 7 - ending Sunday 10th March 2024
Achievements during the week
-
Partition of library area removed
-
Insulation and Ceiling removed from the Library area
-
Fifth foundation pit excavated
-
Building Control Inspected foundation and approved
-
Concrete Foundation mixed and poured
-
Remaining floor beams installed over the library area making provision for staircase and lift
-
Floor board sheets installed over library area completing installation of the upper floor deck
-
Areas of ground floor cleared and cleaned in preparation for plaster boarding out the ceiling