Progress Report - Week  7  -  ending Sunday 10th March 2024

Achievements during the week

  • Partition of library area removed

  • Insulation and Ceiling removed from the Library area

  • Fifth foundation pit excavated

  • Building Control Inspected foundation and approved

  • Concrete Foundation mixed and poured

  • Remaining floor beams installed over the library area making provision for staircase and lift

  • Floor board sheets installed over library area completing installation of the upper floor deck

  • Areas of ground floor cleared and cleaned in preparation for plaster boarding out the ceiling